In August 2018, Orange Village Council awarded a contract to Karvo Paving for asphalt road repairs on Orangedale Road. The project is anticipated to begin the week of September 24th and last approximately four weeks depending on the weather.

The project includes milling the existing pavement, repairing any necessary road base, placing a new base course of asphalt and topping the roadway with a chip seal surface.

Orangedale will be open to two way traffic at all times during the construction.

Orange Tree Development

The project is expected to begin the week of September 24th and last approximately six weeks, depending on the weather.

The project includes milling the existing pavement, repairing any necessary road base, adjusting any needed sewer castings and placing new asphalt in two separate layers.

All the roads will be open to two way traffic at all times during the construction.