Mayor Kathy Mulcahy called the meeting to order at 7:30 pm.

Members Present:	Anthony Lazar (arrived 7:35 pm), Jud Kline, John Terlep, Herb Braverman,
			Scott Lewis, Brian Hitt, Mayor Kathy Mulcahy

Members Absent:		None

Others Present:		Rebecca Schaltenbrand, Asst. Law Director
			Ron Kluchin, Village Architect
			Mary Fisco, PZ/ABR Secretary
#1	FENCE						- Ron Fisher, Owner
							- 305 Capitol Hill Circle
							- Great Lakes Fence Co.
Present:  Ron Fisher					- Ron Fisher, Representative

PZ/ABR Discussion:  Joint motion to approve was made by Hitt; seconded by Lewis.  

Ayes:	Lazar, Kline, Terlep, Lewis, Braverman, Hitt, Mulcahy
No:	None

#2	STORAGE SHED					- Ernest Szolnoky, Owner
							- 4611 Brainard Rd.
							- Storage Building Unlimited
							- Ernest Szolnoky, Representative
Present:  Ernest Szolnoky

PZ/ABR Discussion:  Mr. Szolnoky was made aware the Orange Village Code requires storage sheds 
are required to be placed on a concrete slab with a 12” turned-down edge.   Mr. Szolnoky noted he was not 
aware of this requirement, but believes his contractor was planning on placing the building on a foundation.  
Mr. Szolnoky indicated he would like to install footers instead of the slab. The proponent noted he would 
speak to his contractor to see determine what was actually intended, what are his options and then get 
back to the building department with the required documentation.

No Action Taken.

#3	DECK						- Eliot & Helene Gelb, Owner
							- 250 Jackson Rd.
							- Allan Pearl, Representative
Present:  Mr. Allan Pearl

PZ/ABR Discussion:  Joint motion to approve was made by Lewis; seconded by Hitt.

Ayes:	Lazar, Kline, Terlep, Lewis, Braverman, Hitt, Mulcahy
No:	None

#4	ANY OTHER TOPIC FOR DISCUSSION

·	Tom Shields is sending out high-grass letters to residents.
·	Per Jud Kline, the new construction house located at 29900 Emery Road will be an ICF house and 
	is pursuing the Orange Goes Green Certification program.  The contractor (Alan Brown, Premier Builders) has also 
	acquired the remaining adjacent buildable lots on Emery Road and plans to make it a “green subdivision”.  
	Jud Kline and Alan Brown were both interviewed by The Plain Dealer and a newspaper article will be 
	printed on May 	16th about the ‘green initiative’.
·	Herb Braverman is working on getting a fence installed for Herb’s Community Garden.

Motion to approve the minutes of the April 20, 2010 meeting was made by Terlep; seconded by Kline.

Ayes:	Lazar, Kline, Terlep, Lewis, Braverman, Hitt, Mulcahy
No:	None

There being no further business, the meeting was adjourned at 8:10 pm.


_______________________________________            _______________________
Mary Fisco,  PZ/ABR Secretary				    Date




Archives 2005 3-05 | 4-05 | 5-05 | 6-05 | 7-05 | 9-05 | 10-05 | 11-05
Archives 2006 1-06 | 3-06 | 4-4-06 | 4-18-06 | 5-06 | 6-06 | 9-06 | 10-3-06 | 10-17-06 | 11-17-06 | 11-21-06 | 12-12-06
Archives 2007 1-07 | 1-17-07 | 2-6-07 | 2-20-07 | 3-07 | 3-20-07 | 4-3-07 | 4-17-07 | 5-1-07 | 5-15-07 | 6-07 | 6-19-07 | 7-17-07 | 8-7-07 | 8-21-07
9-4-07 | 9-18-07 | 10-2-07 | 10-16-07 | 11-07 | 11-20-07 | 12-04-07 | 12-20-07
Archives 2008 1-15-08 | 2-19-08 | 3-18-08 | 4-1-08 | 4-15-08 | 5-6-08 | 5-20-08 | 6-3-08 | 6-17-08 | 7-1-08 | 7-15-08 | 8-5-08 | 8-19-08 | 9-2-08 | 9-16-08 | 11-18-08
Archives 2009 1-6-09 | 1-20-09 | 2-3-09 | 3-3-09 | 3-17-09 | 4-7-09 | 4-21-09 | 5-19-09| 6-2-09 | 6-19-09 | 7-7-09 | 7-21-09 | 8-18-09 | 9-1-09 | 9-15-09 | 10-6-09 | 10-20-09 | 12-15-09
Archives 2010 1-19-10 | 2-2-10 | 2-16-10 | 3-2-10 | 4-6-10



ORANGE VILLAGE 4600 Lander Rd. Orange Village, Ohio 44022 440-498-4400